The Condong plant consists of a single 150 t/h boiler, a single steam driven 30MW turbo alternator and auxiliary plant systems (such as water treatment, ash handling, fuel handling and on-line storage) to support the main plant operation.
Plant cooling will be by evaporative cooling towers. The plant will provide steam, extracted from the turbine, to the mill for heating and motive power. Primary condensate will be returned to the cogeneration plant.
A fuel stockpile area has been developed as part of the EPC contract to store surplus cane-based fuel and other fuels. This area comprises approximately 6ha of hardstand with a perimeter earth wall to keep floodwaters from the fuel. A transfer conveyor between the cogeneration plant and the stockpile area is included.
Construction progess
Construction progress for Condong is provided in regular newsletters to local residents. Copies of newsletters are provided through the links below.
Newsletters - June 2008 - October 2007  - February 2007  - February 2006  - November 2005

|
|
|